SuperValu Freezer Building
Return to Client List

Triangle needed to maintain absolute air and water-tight conditions throughout this extremely challenging project.
The job required Triangle to strip the old roof down to a severely deteriorated steel deck, replace that deck, and then install nine inches of new roofing insulation in seven layers. The extra thickness of the new installation required Triangle to raise critical ammonia lines and electrical conduits by several inches. Loose laid EPDM from Johns Manville and loose aggregate for ballast topped the layers of insulating materials.